Building our Future in Yakima

06/20/2019

building exterior illustration

Baker Boyer is building a new facility to meet the expanding needs of the Yakima Valley. It will be completed in Spring 2020. This is in stark contrast to many financial services firms that have exited the market in favor of remote phone and web-based service only. In their article, "Connected communities: unite by design," our design partner, NewGround, explains how this new development is much more than a building. 

On this page, we’ll track the progress of the project with highlights, photos, and video. We’ll keep the most current update on the top of the page.

For more details about the project, please read this article. In addition, many more photos and video can be viewed in this album on our Facebook page

June 2019 – Pouring Foundations

With the site prepped and forms in place, most of the pouring of the foundation cement was completed in just one day. In addition to the photos below, please click here for drone video footage, shot by G-Force Aerial Media

aerial pouring cement

Cement Worker

May 2019 – Excavation and forms work

Excavation and forms work begins to prepare for foundations. 

site work 3

site construction 4

April 2019 – Site Preparations Begin

The construction is a double lot on the hillside across the street above the current location. Initial site preparations included the relocation of a sewer line and site grading.

starting site prep

starting site prep 2

March 2019 - Ground Breaking Ceremony

On Thursday, March 7, Baker Boyer held a ceremonial groundbreaking ceremony which included with remarks from Megan Clubb, Chairman, Board of Directors. In addition to members of Baker Boyer’s Executive Committee and Yakima office staff, attendees included: Charlie Eglin of Tri-Ply (general contractor), Cory Trapp of Longwell + Trapp Architects (architect), and Shiela Finely of NewGround (facility designer).

groundbreaking ceremony

December 2018 – Announcement

At its December meeting, the Board of Directors of Baker Boyer authorized the construction of a $10.5 million new branch in Yakima, which includes both the cost of land and construction. The building will be approximately 19,000 square feet.  It will house offices for Baker Boyer advisors and staff, client meeting and conference rooms, and new backup & recovery space for our IT group. It will also feature a large community conference space for up to 100 people designed to serve professionals and non-profits in the area, as well as Baker Boyer functions.

For more details, read the full announcement here.

Here is media coverage of the announcement: